A new or heavily restructured asset is not sold or refinanced on the strength of practical completion of the works alone. When the data room opens, the institutional purchaser and the lender ask for the same document: proof that the conformity of the works with the planning permission can no longer be challenged by the municipality. This proof is built, not improvised: it requires a properly prepared declaration of completion and conformity of the works (déclaration attestant l'achèvement et la conformité des travaux, DAACT), accompanied by the right certificates, filed on a date from which a three-month or five-month period runs. This guide treats the DAACT for what it is in a transaction: a timetable milestone, whose filing, processing, possible challenge and clearing determine the signing date and the drawdown date.
The DAACT: last act of the permission, first document in the disposal file
Article L. 462-1 of the French Town Planning Code lays down the rule: on completion of the construction or development works, a declaration certifying that completion and the conformity of the works with the permit issued or the prior declaration is sent to the town hall. Since Law No. 2021-1104 of 22 August 2021, the same text extends this obligation to demolition and restoration works carried out under Article L. 121-22-5, as part of adaptation to coastal erosion. In that case, conformity is assessed against the order requiring performance of the demolition obligation, and not against a permit.
The DAACT is not a harmless declaratory formality. It triggers the only mechanism that closes the risk of an administrative challenge to conformity. As long as it has not been filed, the municipality's review period has not begun to run, and the asset's exposure remains open-ended.
Who prepares the declaration, and how
Article R. 462-1, in the wording resulting from Decree No. 2026-674 of 27 July 2026, provides that the declaration is prepared by the beneficiary of the building or development permit or of the decision of non-opposition to the prior declaration, or by the architect or the person approved in architecture where they have directed the works. The change of verb compared with the previous wording, which referred to the declaration being "signed by", is worth noting in arrangements where project ownership is delegated: the author of the act remains exhaustively designated.
Transmission follows two routes, and only two: registered letter with postal acknowledgement of receipt to the mayor of the municipality or delivery against a receipt at the town hall. The mayor then forwards the declaration to the prefect where the permit or non-opposition was issued in the name of the State, or to the president of the inter-municipal cooperation body where the decision was taken in the name of that body. In operational terms, this point has a direct consequence: the acknowledgement of receipt or the receipt is the document that fixes the date of receipt at the town hall, and therefore the starting point of the review period. It must be kept and placed on file in the same way as the DAACT itself.
Partial declaration, by phase
Article R. 462-2 requires the declaration to state whether completion concerns all or a phase of the works, and, where a developer has been authorised to defer the finishing works on the roads, to mention this. In a phased development, this statement governs how the cleared perimeter is read: a phase DAACT clears only the phase declared. A purchaser who reasons on the whole transaction from a certificate covering one phase makes an error of perimeter.
The "works conformity certificate" no longer exists
The expression is still used by practitioners and in purchasers' requests, but it has corresponded to no document since the reform of planning permissions that came into force on 1 October 2007. The authorities no longer issue a conformity certificate: they have a period in which to challenge conformity and, failing a challenge, issue a certificate that conformity of the works has not been challenged (Article R. 462-10). The nuance is not semantic. The document does not certify that the works are conforming; it certifies that the municipality did not exercise its power of challenge within the period. Drafting a condition precedent to a sale by referring to a "certificat de conformité" exposes the parties to a condition without object.
The supporting documents: what determines the effectiveness of the filing
The DAACT is not a stand-alone form. Several certificates accompany it as of right, and their absence weakens the filing at the very moment the developer is seeking to start the period running.
Article R. 462-4-1 requires the attestation of compliance with the energy and environmental performance requirements to be attached, where it is required under Article R. 122-24-3 of the French Construction and Housing Code, or the attestation of compliance with the thermal regulations where it is required under Article R. 122-24 of the same code. Decree No. 2023-1175 of 12 December 2023 replaced the former "taking into account" wording with a compliance standard, which hardens the scope of the document for operations subject to RE2020.
For its part, Article R. 462-4 requires, in the cases provided for in Articles R. 122-37 and R. 122-38 of the French Construction and Housing Code, attestations of compliance with the earthquake-resistant construction rules and with the rules relating to the risk of shrinkage and swelling of clay soils. A transitional regime, common to both texts, allowed these attestations to be made under the earlier provisions for buildings whose permit application had been filed before 1 January 2024 and whose DAACT was filed before 1 January 2025. At the time of writing, this regime has lapsed for pending filings: the attestations must meet the requirements resulting from the decrees of 12 December 2023.
Finally, for subdivision operations carried out in phases, Article R. 462-3, in the wording resulting from Decree No. 2024-1043 of 18 November 2024, requires the DAACT for a phase to be accompanied by evidence of the completion guarantee for the works of the following phase, established under the conditions of Article R. 442-14. This text applies only to planning permission applications filed from the expiry of a period of thirty days following publication of the decree. The link with financing is direct: the declaration of completion of a phase cannot usefully be filed if the guarantee for the following phase is not in place.
The conformity review period: three months, five months where an inspection is mandatory
This is the heart of the timetable. Article R. 462-6 provides that, from the date of receipt at the town hall of the declaration of completion, the competent authority has a period of three months in which to challenge the conformity of the works with the permit or the declaration. And it adds that this period is extended to five months where an inspection of the works (récolement) is mandatory under Article R. 462-7.
Systematically reasoning on three months is a frequent error in backward planning, and a costly one where the signing date has been fixed on that assumption. Article R. 462-7 lists exhaustively the cases of mandatory inspection:
- a building listed as a historic monument, the perimeter of a classified remarkable heritage site, a classified site or one in the process of being classified, the inspection then being carried out in liaison with the Architecte des Bâtiments de France (architect for historic buildings) or the representative of the minister responsible for sites;
- works falling under the provisions of the Construction and Housing Code applicable to high-rise buildings or to buildings open to the public, in liaison with the departmental director of fire and rescue services, except for category 5 buildings open to the public with no accommodation;
- works carried out in an area intended to be classified in the core of a future national park whose creation has been taken into consideration, in the core of a delimited national park, or in a nature reserve;
- works carried out in an area covered by a natural risk prevention plan, a technological risk prevention plan or a mining risk prevention plan, the inspection not being mandatory, however, where the plan imposes no rule other than compliance with cyclone-resistant or earthquake-resistant standards or the obligation to carry out a prior study of the suitability of the land.
For a Paris office asset open to the public, or for a restructuring of a building located within the perimeter of a remarkable heritage site, the working assumption is therefore five months, not three. A two-month difference on a closing date translates into carrying costs and margin renegotiation.
The scope of the review must also be understood for what it is. Article R. 462-8 requires the competent authority to inform the beneficiary beforehand before any inspection, and states that the inspection covers the conformity of the works with the provisions mentioned in Article L. 421-6 only. A check of conformity with the building permit is therefore not a check of all construction regulations. A certificate of non-challenge clears neither construction defects nor non-conformities falling under regulatory regimes other than those covered by that text. The distinction between poor workmanship, contractual non-conformity and ten-year defect (désordre décennal), and the warranty each engages, is dealt with in our article on the characterisation of construction defects.
Challenge to conformity and regularisation of non-conforming works
Where it considers that the works are not conforming, the municipality does not cancel anything: it serves a formal notice. Article R. 462-9 provides that the competent authority serves formal notice on the client, within the period in Article R. 462-6, to file an amending application or to bring the works into conformity with the permission granted. This notice is served by registered letter with postal acknowledgement of receipt and recalls the penalties incurred. Since Decree No. 2021-981 of 23 July 2021, the text no longer provides for notification by electronic exchange.
Two branches then open, and the choice between them is an economic trade-off as much as a legal one. Filing an amending application leads to changing the permit to fit the work as built; physical remediation leads to changing the work to fit the permit. The first route preserves the asset but reopens a processing period and a window for third-party challenge; the second ties up corrective works and a budget, but creates no new permission open to challenge. In a matter subject to a bank drawdown constraint, the decisive variable is the clearing timetable, not the gross cost of the works. The situations in which an amendment is enough, and those that require a fresh application, are examined in our article on the amending building permit during construction.
Administrative penalties: a scale raised at the end of 2025
Regularisation of non-conforming works is now negotiated under a significantly heavier financial threat. Article L. 481-1, in the wording resulting from Law No. 2025-1129 of 26 November 2025, allows the competent authority, after an official report has been drawn up under Article L. 480-1 and after inviting the person concerned to submit observations, to order payment of a fine of up to €30,000 and to serve formal notice to bring the works into conformity or to file a regularisation permit application or prior declaration.
The formal notice may be accompanied by a daily penalty of up to €1,000 per day of delay, the total amount of the sums not being able to exceed €100,000. Paragraph III quater adds a fine of up to €30,000 where the person concerned has not complied, within the time allowed, with the obligations prescribed by the formal notice. Two points matter for risk management: objection before the administrative court to the enforceable statement issued in respect of the fine or the daily penalty has no suspensory effect (III bis), and the prefect may take the place of the competent authority by reasoned order after inviting it to act and where there has been no reply within one month (III ter). Article L. 481-2 specifies that the daily penalty runs from notification of the order imposing it until proof of performance, that its recovery is pursued quarter by quarter in arrears, and that the competent authority may, at the quarterly settlement, grant a partial or full exemption if the debtor establishes that the failure to perform is due to circumstances beyond its control.
The attestation of non-challenge: the document expected by the notary and the lender
Once the period in Article R. 462-6 has passed without a challenge, Article L. 462-2 states that the competent authority may no longer challenge the conformity of the works. Article R. 462-10, in the wording resulting from Decree No. 2026-117 of 20 February 2026, organises the formal recording of this silence: where the authority remains silent within the period, the competent authority issues as of right to the beneficiary of the permission or to its successors in title (ayants droit), at their request, an attestation certifying that the conformity of the works with the permit or the declaration has not been challenged, within fifteen days of the request being made.
Three practical lessons follow. First, the attestation is not issued spontaneously: it requires a request, which must appear in the timetable on the day after the review period expires. Second, issue is framed by a fifteen-day period, which makes it possible to secure a signing date. Third, the text expressly refers to the beneficiary's successors in title: a purchaser of the asset may make the request, which is valuable where the seller, a dissolved developer or an uncooperative transferor, does not ask for it.
No text read requires this attestation as a mandatory document for the sale of real property. Requiring it is a matter of notarial practice and financing documentation, and it is generally expressed as a condition precedent or a drawdown condition. The consequence is clear from the standpoint of contract drafting: the document's force comes from the contract, not from the law. A promise to sell that merely stipulates delivery of a "conformity attestation" without referring to Article R. 462-10, without specifying the perimeter (whole or phase) and without addressing the case of a formal notice received during the period leaves the purchaser with a dispute over characterisation rather than a guarantee.
What remains exposed after the period has run
It would be imprudent to present the attestation of non-challenge as immunity. Three regimes continue to have effect.
The administration's right of visit and communication, organised by Article L. 461-1 in the wording resulting from Law No. 2025-391 of 30 April 2025, may be exercised up to six years after completion of the works, with a specific regime for the installations and structures referred to in Articles L. 111-27 to L. 111-29, for which it is exercised throughout their period of operation, within a limit of six years after its end or until their authorisation expires.
The administrative limitation rule in Article L. 421-9 then applies, but in a narrow field. Where a building has been completed for more than ten years, refusal of a building permit or a decision opposing a prior declaration may not be based on the irregularity of the original construction under planning law. This text does not regularise the construction: it only prohibits one ground for refusal. And it has seven exceptions, including exposure of users or third parties to a risk of death or of injury causing mutilation or permanent disability, the bringing of a demolition action under the conditions of Article L. 480-13, location in a national park, a classified site or on public land, construction without any building permit having been obtained where one was required, the zones referred to in 1° of II of Article L. 562-1 of the French Environmental Code, and, since Law No. 2021-1104 of 22 August 2021, construction without deposit of the sum prescribed by the planning permission.
The risk of demolition, finally, is governed by Article L. 480-13. Where a building has been erected in accordance with a building permit, the owner may be ordered by the civil courts to demolish it only if, beforehand, the permit has been annulled for abuse of power and, except where the prefect brings the matter on the basis of the second paragraph of Article L. 600-6, only if the building is located in one of the exhaustively listed zones (mountain areas, coastline, registered or classified sites, surroundings of historic monuments, remarkable heritage sites, risk prevention plan zones, areas delimited under Articles L. 151-19 and L. 151-23, among others). The demolition action must be brought within two years following the decision of the administrative court becoming final. As for the civil liability action against the builder, it must be brought no later than two years after completion of the works. For an investor acquiring a recent asset, this second deadline is a valuation parameter: it may already have expired on the day of the sale. On the time limits open to third parties to challenge the permission itself, see our analysis of third-party appeals against a building permit.
The tax aspect of the completion milestone: ninety days
The same triggering event, completion, gives rise to a tax obligation on a separate timetable. Article 1406 of the French General Tax Code requires new constructions, as well as changes in the make-up or use of built and unbuilt property, to be brought by owners to the attention of the tax authorities within ninety days of their final completion. II of the same article makes the benefit of temporary property tax exemptions conditional on declaring the change that justifies them, and specifies that, where the declaration is filed late, the exemption applies for the period remaining to run after 31 December of the following year.
This ninety-day period has nothing to do with the periods in Article R. 462-6. Confusing them directly costs net yield: a late declaration cuts the temporary exemption from property tax on built property, a line that weighs on the business plan of a new asset held in a portfolio.
Managing the DAACT as a transaction timetable milestone
Good practice is to enter five dates in the timetable, not just one: the filing date (with prior preparation of the attestations under Articles R. 462-4 and R. 462-4-1 and, where applicable, of the completion guarantee for the following phase under Article R. 462-3), the date of receipt at the town hall evidenced by the acknowledgement of receipt or the receipt, the expiry of the three-month or five-month period depending on whether an inspection is mandatory within the meaning of Article R. 462-7, the request for the attestation under Article R. 462-10 and its issue within fifteen days, and the tax declaration within ninety days of final completion.
On the purchaser's or lender's side, the audit runs in the opposite direction. The question is not "is there a DAACT?" but: was the declaration prepared by a person authorised within the meaning of Article R. 462-1; does it cover the whole or a phase; is the date of receipt at the town hall proved; was the applicable period three or five months; was a formal notice under Article R. 462-9 served; is there an official report under Article L. 480-1 or an order under Article L. 481-1 in the file. The absence of a documented answer to any of these questions justifies a condition precedent, a price retention or a specific guarantee, and not a mere statement by the seller.
Conclusion
The DAACT is not the administrative close of a building site, it is the act that fixes the end of the planning risk and, as a result, the date on which the asset becomes saleable and refinanceable on normal terms. Our position is clear: a transaction timetable that places signing before the expiry of the period in Article R. 462-6 shifts onto the purchaser or the lender a risk that the penalties in Article L. 481-1, raised by Law No. 2025-1129 of 26 November 2025, now make costly. Before fixing a closing date or a drawdown schedule, have it determined in writing whether your transaction falls within one of the cases of mandatory inspection in Article R. 462-7: it is that determination, and not a three-month assumption applied by default, that fixes the date on which you will have the attestation of non-challenge.
Frequently asked questions
Does the municipality always have three months to challenge the conformity of the works?
No. Article R. 462-6 of the French Town Planning Code sets a period of three months from the date of receipt of the declaration at the town hall, but this period is extended to five months where an inspection of the works is mandatory under Article R. 462-7. The inspection is mandatory in particular for buildings listed as historic monuments, within the perimeter of a classified remarkable heritage site, for high-rise buildings and buildings open to the public (except category 5 without accommodation), in the cores of national parks and nature reserves, and in areas covered by a risk prevention plan, subject to the reservation in d) of that text. A timetable fixed on three months in a matter falling within these cases is wrong by two months.
Does the works conformity certificate still exist?
No. Since the reform of planning permissions that came into force on 1 October 2007, the authorities no longer issue a conformity certificate. The document available is the attestation certifying that the conformity of the works with the permit or the declaration has not been challenged, provided for in Article R. 462-10. It records the absence of a challenge within the period allowed, not the intrinsic conformity of the structure. Contractual clauses referring to a "certificat de conformité travaux" must be rewritten by reference to Article R. 462-10.
How can the attestation of non-challenge of conformity be obtained and within what time?
It is not issued automatically. Article R. 462-10, in the wording resulting from Decree No. 2026-117 of 20 February 2026, provides that where the competent authority remains silent within the period in Article R. 462-6, it issues the attestation as of right to the beneficiary of the permission or to its successors in title, at their request, within fifteen days of the request being made. The request must therefore be sent as soon as the review period expires. The reference to successors in title allows the purchaser of the asset to request it itself.
Can a purchaser ask for the attestation if the seller has not done so?
Yes, Article R. 462-10 expressly refers to the successors in title of the beneficiary of the permission. In practice, this right is secured in advance: the promise to sell provides for production of the DAACT and proof of its receipt at the town hall, as well as an undertaking by the seller to request the attestation and, failing that, an authorisation given to the purchaser to request it. No text requires the attestation as a mandatory document for the sale; its force comes from the contractual stipulation.
What penalties does a client face whose works do not comply with the permit?
After an official report drawn up under Article L. 480-1 and after inviting the person concerned to submit observations, the competent authority may, under Article L. 481-1 resulting from Law No. 2025-1129 of 26 November 2025, order a fine of up to €30,000 and serve formal notice to regularise or bring the works into conformity. The formal notice may be accompanied by a daily penalty of up to €1,000 per day of delay, the total not exceeding €100,000, and an additional fine of up to €30,000 may be imposed if the formal notice is not complied with. Objection to the enforceable statement before the administrative court has no suspensory effect. Criminal proceedings may be brought independently of these measures.
Is a building completed more than ten years ago regularised as of right?
No, and the confusion is frequent. Article L. 421-9 provides only that, where a building has been completed for more than ten years, refusal of a building permit or a decision opposing a prior declaration may not be based on the irregularity of the original construction under planning law. It confers no regular title on the structure. Seven exceptions also neutralise this rule, including the total absence of a permit where one was required, location in a classified site, in a national park or on public land, and, since Law No. 2021-1104 of 22 August 2021, construction without deposit of the sum prescribed by the permission.
What is the tax time limit to observe after completion of the works?
Article 1406 of the French General Tax Code requires new constructions and changes in make-up or use to be brought to the attention of the tax authorities within ninety days of their final completion. The benefit of temporary property tax exemptions is conditional on this declaration; if it is filed late, the exemption applies only for the period remaining to run after 31 December of the following year. This period is autonomous and is not to be confused with that in Article R. 462-6.
The simulator below tells you which planning permission is required, the processing times, the appeal deadlines and how long the permit remains valid.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationDefects that appeared after handover?
One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.