Private fixed-price works contract (Art. 1793 Civil Code): the additional works the employer does not have to pay for

A claim statement (mémoire de réclamation) arrives three weeks after acceptance of the works: the general contractor prices additional works representing a significant fraction of the contract, on the ground that the employer (maître d'ouvrage) "knew", that the site meeting minutes refer to them and that the building as delivered could not have been completed otherwise. The question put to the property department or the finance department is not an accounting one, it is a contractual one: a fixed-price contract (marché à forfait) has been signed, and Article 1793 of the French Civil Code makes any increase in price subject to two cumulative conditions that most end-of-project claims do not satisfy. This guide sets out the conditions for the fixed price to apply in a private works contract, the exact content of the twofold requirement of written authorisation and agreed price, the grounds invoked by contractors to get round the rule, the evidential position, and how to respond to a claim for the balance.

The text of Article 1793 and its scope

The letter of the rule

Article 1793 of the French Civil Code, in a wording unchanged since 1804, provides:

Where an architect or a contractor has undertaken the construction of a building at a fixed price, according to a plan settled and agreed with the owner of the land, he may not claim any increase in price, whether on the pretext of an increase in labour or materials, or on that of changes or additions made to that plan, if those changes or additions have not been authorised in writing, and the price agreed with the owner.

Four elements govern the application of the text: an architect or a contractor, a fixed-price construction, a building, and a plan settled and agreed with the owner of the land. These terms are those of the Code. The exact scope that the case law gives them (what qualifies as a "building", the degree of precision of the plan, the position of major renovation, refurbishment or civil engineering contracts, the situation of project management contracts) is the subject of a body of case-by-case decisions that must be checked file by file before a defence is based exclusively on Article 1793. For an institutional employer, the operational consequence is immediate: never rest the protection of the fixed price on the statutory text alone, but back it with a contractual structure that produces the same effect whatever characterisation is adopted.

Extension to separate trades

Article 1793 does not concern only the general contractor. Article 1799 of the French Civil Code provides that masons, carpenters, locksmiths and other workmen who contract directly for fixed-price work are bound by the rules laid down in this section: they are contractors in respect of the part they undertake. An employer who divides its project into separate lots, each entrusted at a fixed price, therefore benefits from the same regime lot by lot. The point deserves emphasis, because claims for additional works frequently arise on the technical lots, where the boundary between an adjustment in execution and a change to the programme is the least clear.

The civil-law foundation of the intangibility of the fixed price

Even where the application of Article 1793 is disputed, the fixed price remains protected by the general law of contract resulting from Ordinance No. 2016-131 of 10 February 2016, in force since 1 October 2016. Article 1103 provides that contracts lawfully formed have the force of law for those who have made them. Article 1193 adds that contracts may be modified or revoked only by the mutual consent of the parties, or for reasons authorised by law. A change in the price therefore requires an agreement, that is to say an amendment (avenant). This subsidiary line of defence is robust: it depends neither on the characterisation as a building nor on the existence of a settled plan.

The two cumulative conditions: written authorisation and agreed price

The wording of Article 1793 is often quoted in truncated form, as if a writing were enough. The text requires that the changes or additions have been authorised in writing, and the price agreed with the owner. The two conditions are cumulative.

The practical consequences are considerable. A contractor that produces a works order (ordre de service) signed by the employer describing a technical change, but silent on its financial impact, has satisfied only the first condition. Likewise, an email from the programme director approving a change in the type of flooring, with no quotation accepted, does not amount to agreement on the price. The employer's defence then consists of setting out, document by document, the separation between technical authorisation and financial agreement.

The converse is equally true: a supplementary quotation sent by the contractor and left unanswered constitutes neither written authorisation nor an agreed price. The employer's silence does not amount to acceptance, and a document originating from the contractor is not a document from the owner. This is why, in defence, the contractor's production of a bundle of unreturned quotations generally weakens its position more than it strengthens it: it shows that the contractor knew the contractual procedure and did not follow it through.

What the text expressly excludes: rising costs

Article 1793 prohibits the contractor from claiming an increase on the pretext of an increase in labour or materials. A rise in the price of materials, energy or wages is therefore not, in itself, a ground for increasing the fixed price. The text says so expressly, and it is one of the rare cases where the Civil Code names the very reason that it rejects.

Contractors then move the debate onto the ground of unforeseeability (imprévision). Article 1195 of the French Civil Code, resulting from the same 2016 ordinance, allows a party to request renegotiation if a change in circumstances that was unforeseeable at the time of the conclusion of the contract makes performance excessively onerous for a party who had not agreed to bear the risk. The text specifies that that party continues to perform its obligations during the renegotiation; if renegotiation fails, the parties may agree to terminate the contract, or may jointly ask the court to adapt it; failing agreement within a reasonable time, the court may, at the request of a party, revise the contract or put an end to it.

Two observations are called for from the employer's point of view. First, the relationship between Article 1195 and the express prohibition in Article 1793 is a matter of debate, not a settled solution: it is arguable that the special provision on fixed-price contracts, which expressly refers to the increase in materials and labour, precludes revision. Second, and above all, Article 1195 does not apply automatically: it requires a change that was unforeseeable at the time of conclusion, performance that has become excessively onerous, and a party that had not agreed to bear the risk. A contract signed after a period of known tension on a category of materials, or containing a clause by which the contractor accepts the risk of changes in costs, largely neutralises this ground. An express stipulation accepting the risk, referring to Article 1195, is now a basic clause of any private fixed-price contract concluded by an institutional investor. The conditions of Article 1195 and the drafting of a clause allocating the risk are set out in our article on unforeseeability and hardship clauses in B2B contracts.

The grounds invoked at the end of a project to get round the rule

Tacit acceptance and subsequent ratification

This is the central argument of almost every claim statement: the employer is said to have accepted the additional works by its conduct, by allowing them to be carried out, by signing off site meeting minutes that mention them, by paying interim statements that include them, or by accepting the building without reservation.

One must start from the text. Article 1793 requires nothing other than written authorisation and an agreed price; it provides for no tacit acceptance. The qualifications that have been admitted derive from case law, the scope of which must be checked in each case and which remains, in any event, restrictive in interpretation as a matter of principle. In defence, the strategy consists of challenging each of the facts alleged in order to show that they reflect neither an authorisation nor an agreement on a price.

The appearance of the works in site meeting minutes drawn up by the project manager does not amount to authorisation by the employer: it is a monitoring document, prepared by a third party to the pricing relationship, the circulation of which implies no budgetary approval. The payment of instalments or interim statements likewise does not amount to agreement on a price that was not agreed, where the contract provides for payment as the fixed price progresses and the statements were signed off subject to the final account. As for acceptance of the works (réception), Article 1792-6 defines it as the act by which the employer declares that it accepts the building with or without reservations, made on an adversarial basis, and it starts the one-year completion warranty. The text concerns the conformity and quality of the building, not its price. It nowhere says that acceptance without reservation would amount to acceptance of the cost of additional works, and the opposite assertion, frequent in claim statements, finds no support in the wording of Article 1792-6. On the effect of acceptance and its relationship with payment of the balance, see our analysis of acceptance of works within the meaning of Article 1792-6.

A governance reflex drastically limits this litigation: name in the contract the one person authorised to commit the employer financially, and stipulate that neither the project manager, nor the inspection body, nor the works scheduling and coordination manager (OPC) has that power. The end-of-project claim then runs up against a lack of authority on the part of the person whose agreement the contractor relies on.

Unilateral fixing of the price

The contractor sometimes relies on Article 1165 of the French Civil Code, in its wording resulting from Law No. 2018-287 of 20 April 2018, in force since 1 October 2018 and to which Article 16, I, of that law gives interpretative effect. That text provides that, in contracts for the provision of services, failing agreement of the parties before performance, the price may be fixed by the creditor, who must give reasons for the amount if it is challenged, and that in the event of abuse in the fixing of the price, a claim may be brought before the court for damages and, where appropriate, termination of the contract.

The argument is weak in a fixed-price contract. Article 1165 addresses the case where there is no agreement on the price before performance; yet, in a fixed-price contract, the price has been agreed, and Article 1793 specifically governs the fate of increases. The employer should also note that the text does not create a right to have the unilateral price validated by a court: it provides a sanction for abuse, in the form of damages and, where appropriate, termination of the contract. It does not give the contractor a mechanism for the judicial fixing of the price of unauthorised works.

Unjustified enrichment

The last subsidiary ground is unjustified enrichment, codified in Articles 1303 et seq. of the French Civil Code since Ordinance No. 2016-131, which replaced the former case-law quasi-contract of enrichment without cause. Article 1303 provides that a person who benefits from unjustified enrichment at the expense of another must compensate the person who has been impoverished, in an amount equal to the lesser of the two values of the enrichment and the impoverishment.

Two arguments of defence follow directly from the texts. First, subsidiarity: Article 1303-3 states that the impoverished party has no claim on this basis where another claim is open to it or is barred by a legal obstacle, such as limitation. A contractor that has a contractual claim, or that has run up against the legal obstacle constituted by Article 1793, cannot in principle fall back on unjustified enrichment to get round the rule. Second, the cap: compensation is limited to the lesser of the two values of the enrichment and the impoverishment, which requires the contractor to demonstrate the real added value provided to the building, and not its cost price plus its margin. In a rental operation, demonstrating the enrichment requires establishing an increase in value or in rent, an exercise that claim statements almost never address.

The battle over evidence: what the contractor must establish

The burden of proof is the first ground of the defence. Article 1353 of the French Civil Code provides that a person who claims performance of an obligation must prove it. The claimant contractor must therefore establish the existence of the written authorisation and of the agreement on the price, and the employer need not demonstrate their absence. Any defence that exhausts itself in proving a negative takes the wrong procedural position.

Article 1359 adds two locks. On the one hand, a legal act involving a sum or value exceeding an amount fixed by decree must be proved in writing, either under private signature or by notarised deed. On the other hand, and irrespective of any threshold, it may not be proved in addition to or against a writing establishing a legal act, even if the sum or value does not exceed that amount, except by another writing under private signature or by notarised deed. As the fixed-price contract is itself a writing, claiming to prove by witnesses or by presumptions an agreement increasing the price that it fixes amounts to proving in addition to that writing. The text bars this. Paragraph 3 finally condemns a classic tactic: a person whose claim exceeds the threshold mentioned in the first paragraph cannot be exempted from the requirement of written proof by limiting the amount claimed, and the same applies to a person whose claim, even if lower, relates to the balance or to part of a larger claim. Splitting an overall claim into individual items therefore does not open the door to free proof.

There remains the commencement of proof in writing (commencement de preuve par écrit), by which the contractor attempts to soften the requirement. Article 1362 defines it as any writing which, emanating from the person who disputes an act or from the person he represents, makes what is alleged probable. The condition as to origin is decisive: the writing must emanate from the employer or its representative. A quotation from the contractor, an email from its site manager, an unsigned works order, minutes drawn up by the project manager do not emanate from the employer. The same article specifies that statements made at a personal appearance, a refusal to answer or a failure to appear may be treated as equivalent: a further reason to prepare carefully the representation of the institutional employer if a personal appearance is ordered.

The timetable: acceptance, final account and limitation

The claim for additional works almost always arises at the time of the final account, because that is the moment when the contractor measures its result on the project. The employer has an interest in organising this sequence contractually: time limit for production of the final claim statement, contractual foreclosure of claims not submitted within that time limit, final character of the accepted account. These mechanisms come within contractual freedom and the special documents of the contract; they derive from no provision of the Civil Code and must therefore be expressly stipulated. The content of each account, the claim statement and the time limits attaching to it are dealt with separately in our article on the final general account (décompte général définitif).

As regards limitation, the contractor's claim for payment is in principle subject to a five-year period, whether one relies on Article 2224 of the French Civil Code, which provides that personal or movable claims are barred after five years from the day on which the holder of a right knew or should have known the facts enabling it to exercise that right, or on Article L. 110-4, I, of the French Commercial Code for obligations arising in the course of their trade between traders or between traders and non-traders. Article L. 110-4, II, 3°, also provides for the limitation of claims for payment for work done, one year after acceptance of the work, but the scope of that provision, inserted among special limitation rules of a maritime context, must be checked against case law before it is relied on. A plea of inadmissibility based on a one-year period should be made only after that check; it is not to be presumed.

The contractor's counter-arguments and confusions to avoid

The payment guarantee under Article 1799-1

Faced with a refusal to pay, the contractor often relies on Article 1799-1 of the French Civil Code, which requires an employer entering into a private works contract covered by 3° of Article 1779 to guarantee payment of the sums due where they exceed a threshold fixed by decree of the Conseil d'État. Article 1779, 3°, covers the hire of work of architects, building contractors and technicians following studies, quotations or contracts. Failing a specific credit facility and any particular stipulation, payment is guaranteed by a joint and several surety given by a credit institution, a finance company, an insurance undertaking or a collective guarantee body, the reference to finance companies resulting from Ordinance No. 2013-544 of 27 June 2013, in force on 1 January 2014. The text adds that, as long as no guarantee has been provided and the contractor remains unpaid for the works carried out, the contractor may suspend performance of the contract after a formal notice that has remained without effect at the end of a period of fifteen days.

Two limits should be noted on the employer's side. The guarantee covers sums due under the contract, not a disputed claim for additional works whose very existence is contested. And Article 1799-1 expressly excludes from its scope contracts entered into by a body referred to in Article L. 411-2 of the French Construction and Housing Code, or by a semi-public company (société d'économie mixte), for rental housing subsidised by the State and built by that body or company. Social landlords and the semi-public companies concerned should be aware of this exclusion, which changes the balance of power during the project.

Not confusing a refusal to pay with termination under Article 1794

An employer that disputes additional works must not slide towards a de facto breach of the contract. Article 1794 allows the employer to terminate the fixed-price contract by its sole will, even though the work has already begun, but by compensating the contractor for all its expenses, all its work, and all that it could have earned in that undertaking. Compensation therefore includes loss of profit. A decision to stop the works taken under pressure of an abusive claim can turn litigation that is winnable on the ground of Article 1793 into certain compensation on that of Article 1794.

Not importing the vocabulary of the CCMI

Finally, claim statements and improvised defences alike sometimes borrow from the regime of the contract for the construction of a single-family house with supply of the plan (CCMI). Article L. 231-2 of the French Construction and Housing Code requires an agreed price that is fixed and final, subject to its revision within the conditions and limits agreed in accordance with Article L. 231-11, and makes works that the employer reserves to itself subject to a specific handwritten and initialled clause. This formality protects a consumer employer under a distinct regime; it cannot be transposed to the ordinary private works contract governed by Article 1793.

Conclusion: the defence is built at signing, not at acceptance

Article 1793 of the French Civil Code is one of the most protective provisions available to an employer in a private works contract, provided it is not relied on alone and late. Its strength lies in the twofold cumulative condition it lays down: written authorisation of changes, and a price agreed with the owner. Its fragility lies in its scope, the contours of which depend on case-law assessment and which does not cover every operation. The remedy is well known: back the fixed price with contractual stipulations that produce the same effect independently of Article 1793, set up a single written procedure for financial commitment, refuse any technical approval that is not accompanied by an accepted price, and treat interim statements as subject to express reservation of the final account.

Faced with a claim statement, the sequence of defence is as follows: recall that the burden of proof lies on the contractor, sort the documents according to whether or not they emanate from the employer within the meaning of Article 1362, separate in each alleged authorisation the technical aspect from the financial aspect, check limitation, and enter into settlement negotiations only after having quantified the real exposure. Before signing the next contract, have the pairing of fixed-price clause and change works order procedure reviewed by legal counsel: it is at this stage, and not at the end of the project, that litigation over additional works is won.

Frequently asked questions

Is a works order signed by the employer enough to make additional works payable?

No, not on its own. Article 1793 of the French Civil Code requires that the changes or additions have been authorised in writing, and the price agreed with the owner. The two conditions are cumulative. A works order that describes a technical change without fixing or accepting its financial impact satisfies only the first. In defence, it is necessary to check systematically whether each document produced by the contractor contains an agreement on the price, and not merely approval of the work.

Does acceptance without reservation amount to acceptance of the additional works and their price?

Article 1792-6 of the French Civil Code defines acceptance as the act by which the employer declares that it accepts the building with or without reservations, made on an adversarial basis, and it starts the one-year completion warranty. The text concerns acceptance of the building, not acceptance of a price. It nowhere provides that acceptance without reservation would amount to agreement on the cost of unauthorised works. The argument, frequent in claim statements, finds no support in the wording of Article 1792-6.

Does Article 1793 apply to contracts divided into lots by separate trades?

Yes. Article 1799 of the French Civil Code subjects to the rules of the same section masons, carpenters, locksmiths and other workmen who contract directly for fixed-price work, specifying that they are contractors in respect of the part they undertake. An employer that contracts lot by lot at a fixed price therefore benefits from the fixed-price regime on each lot, subject to the other conditions of application of Article 1793.

Can the contractor obtain a revision of the fixed price because of a rise in the price of materials?

Article 1793 expressly excludes any increase claimed on the pretext of an increase in labour or materials. The contractor then turns to Article 1195 of the French Civil Code, which requires a change of circumstances that was unforeseeable at the time of conclusion, performance that has become excessively onerous, and a party that had not agreed to bear the risk. The relationship between that text and the prohibition in Article 1793 remains debated. In practice, a clause by which the contractor expressly accepts the risk of changes in costs, referring to Article 1195, removes the basis of the argument.

Does unjustified enrichment allow the contractor to get round Article 1793?

Only with difficulty. Since Ordinance No. 2016-131 of 10 February 2016, unjustified enrichment has been codified in Articles 1303 et seq. of the French Civil Code. Article 1303-3 bars the claim where another claim is open to it or is barred by a legal obstacle, such as limitation. Article 1303 also caps compensation at the lesser of the two values of the enrichment and the impoverishment, which requires the contractor to demonstrate the added value actually provided to the building, and not its cost price.

What limitation period applies to a claim for additional works at the end of a project?

The general period is five years, on the basis of Article 2224 of the French Civil Code for personal claims, or of Article L. 110-4, I, of the French Commercial Code for obligations arising in the course of trade. Article L. 110-4, II, 3°, also mentions a limitation of claims for payment for work done, one year after acceptance of the work, but the scope of that provision must be checked against case law before it is relied on in defence. It is better to base the plea of inadmissibility principally on the five-year period.

Can an employer stop the works to put pressure on a contractor faced with a claim?

This is a major risk. Article 1794 of the French Civil Code allows the employer to terminate the fixed-price contract by its sole will, even though the work has begun, but by compensating the contractor for all its expenses, all its work, and all that it could have earned in that undertaking, loss of profit included. In addition, Article 1799-1 allows an unpaid contractor to suspend performance where no payment guarantee has been provided, after a formal notice that has remained without effect at the end of a period of fifteen days. A claim should therefore be contested in writing and in the account, not by an interruption of the works.

The simulator below tells you, from the date of acceptance of the works, which guarantee covers your defect and until when you can act.

Votre situation ressemble-t-elle à celle-ci ?

Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.

Décrire ma situation
Sans engagement – réponse du cabinet sous quarante-huit heures ouvrées.
• Vous êtes concerné ?

Defects that appeared after handover?

One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.

construction
private-fixed-price-works-contract-art-1793-civil-code-additional-works
Questionnaire
×
Merci, votre demande est bien parvenue au cabinet. Une réponse vous sera adressée sous quarante-huit heures ouvrées.
L’envoi n’a pas abouti. Vous pouvez écrire directement à contact@avocats-gloria.com.

Vos réponses aux questions précédentes sont jointes à votre message. Réponse sous quarante-huit heures ouvrées.

Ces questions ne constituent pas une consultation juridique et ne remplacent pas l’examen de vos pièces. Les informations transmises servent uniquement à répondre à votre demande et ne sont pas cédées à des tiers.