The legal department receives the draft framework agreement (contrat-cadre) three weeks before the 1 March deadline, with a grid of penalties, a clause allowing unilateral revision of the price and an asymmetric termination mechanism. The chief executive wants to sign to secure the volume of business; the chief financial officer (DAF) sees an unprovisioned exposure. Since Law No. 2026-796 of 18 August 2026, which entered into force on 20 August 2026, Article L. 442-1 of the French Commercial Code has been widened: a new point 6° targets repeated competitive tendering, and paragraph II now penalises, under conditions, a substantial reduction in order volumes negotiated during the course of a relationship. This guide sets out the method for auditing a framework agreement against the significant imbalance (déséquilibre significatif) rule, the real measure of the financial and procedural exposure, and the criteria for choosing between renegotiation and litigation.
What exactly Article L. 442-1, I, 2° of the Commercial Code penalises
The seat of the subject is Article L. 442-1, I, 2° of the Commercial Code. The first reflex to correct is the numbering. Former Article L. 442-6, I, 2° is no longer the text in force. Article L. 442-6 now penalises a different practice, the imposition of a minimum resale price, punishable by a fine of €15,000. Citing "L. 442-6, I, 2°" in a formal notice or a summons immediately signals an analysis that has not been updated.
The text in force makes its author liable and requires that person to compensate the harm caused, for the act, in the context of commercial negotiation, or the conclusion or performance of a contract, by any person engaged in production, distribution or services activities:
"2° Submitting or attempting to submit the other party to obligations creating a significant imbalance in the rights and obligations of the parties"
Three elements of scope deserve the decision-maker's attention. First, the victim is no longer described as a "commercial partner" but as the other party, which considerably widens the range of relationships concerned. Second, the practice is caught at three stages: negotiation, conclusion, performance. A clause signed without reservation can therefore be challenged at the stage of its implementation. Finally, an attempt to impose suffices: a draft contract that is imposed, even if not signed as it stands, may establish the practice.
Submission and imbalance: two distinct conditions
The Code defines neither submission nor imbalance. Both notions derive from case law, following in particular the constitutional review carried out on the earlier wording (Constitutional Council, Decision No. 2010-85 QPC). The courts assess submission from the absence of effective negotiation: standardisation of the contractual documents, absence of any possible counter-proposal, a relationship of dependence or buying power, the shortness of the deadlines imposed for signature. Imbalance, for its part, is assessed in light of the overall economics of the contract: an asymmetric clause may be rebalanced by another stipulation, provided that the counterpart is identifiable and effective.
The operational consequence is direct. A manager who intends to rely on the text must document the absence of negotiation, and not merely show that the clause is unfavourable. Conversely, a company in the position of buyer that wishes to reduce its exposure must keep a record of the exchanges, of the successive versions of the framework agreement and of the concessions obtained by its counterparty. Proof of effective negotiation is the first line of defence.
What the Law of 18 August 2026 added
Paragraph I no longer stops at 5°. A new 6° penalises submitting a commercial partner to repeated competitive tendering procedures or calls for tender whose frequency or arrangements are such as to create a significant imbalance in the rights and obligations of the parties. Purchasing departments that systematically put a long-standing supplier back out to tender at short intervals must revisit their sourcing policy in light of this text. It should be noted that 6° expressly refers to a "commercial partner", whereas 2° refers to "the other party": the personal scope is not identical.
Paragraph II has also been supplemented. In addition to the abrupt termination, even partial, of an established commercial relationship, the following may engage its author's liability: implementing, in the context of negotiating a contract, a substantial reduction in the order volumes sent to a commercial partner, including where it is temporary in nature, if it is such, by its scale, its unusual nature or the conditions in which it occurs, as to compromise the balance of the established commercial relationship. The threat of reduced volumes as a lever in annual negotiations therefore changes its potential characterisation. The regime governing termination of an established relationship, from the calculation of notice to compensation, is discussed in our article on abrupt termination of established commercial relationships.
Caution is called for in applying these two additions to framework agreements already being performed: the codified text contains no apparent transitional provision, and Article 54 of the Law must be consulted before taking any written position on this point.
Why the framework agreement concentrates the risk
Article L. 441-3, I of the Commercial Code provides that the written agreement between supplier and distributor or service provider is drawn up either in a single document, or in a set made up of a framework agreement and implementing contracts. The same text requires that this agreement set out the reciprocal obligations resulting from the negotiation in compliance with Articles L. 442-1 to L. 442-3. The cross-reference is explicit: review for significant imbalance is not peripheral litigation, it is integrated into the regime of the annual agreement.
The timetable is binding. The agreement is concluded for a term of one year, two years or three years, no later than 1 March of the year in which it takes effect, or within two months of the start of the marketing period for products or services subject to a particular cycle. Where it is multi-year, it sets the arrangements for revising the agreed price, which may incorporate one or more indicators reflecting the change in the price of production factors. Any amendment is recorded in writing stating the new element justifying it. This requirement is a tool for the supplier: a detrimental amendment imposed without an identified new element is legally fragile.
The foundation of the analysis remains Article L. 441-1, III: once drawn up, the general terms of sale (CGV) constitute the sole basis of the commercial negotiation. The gap between the CGV communicated and the purchasing conditions ultimately imposed is the simplest measure of the imbalance alleged. A serious audit begins with this documentary comparison, clause by clause.
Mapping the exposed clauses in a framework agreement
No text lists the clauses that constitute a significant imbalance. The usual illustrations come from decisions handed down and from the work of the Commercial Practices Review Commission (Commission d'examen des pratiques commerciales), and must be handled as such. On the other hand, the Code identifies clauses whose fate is settled in advance. The review should follow that order of priority.
The three clauses that are void by operation of law
Article L. 442-3 renders void clauses or contracts providing, for any person engaged in production, distribution or services activities, the possibility:
- of benefiting retroactively from discounts, rebates or commercial cooperation agreements;
- of automatically benefiting from the more favourable conditions granted by the counterparty to competing businesses;
- of prohibiting the counterparty from assigning to third parties the claims it holds against that person.
The list is exhaustive but does include three limbs since Law No. 2020-1508 of 3 December 2020, which added (c). This third case directly concerns finance departments: a clause prohibiting assignment of receivables inserted in a framework agreement neutralises factoring and the mobilisation of trade receivables. It is void. The point deserves to be checked in any financing documentation secured on trade receivables.
Logistics penalties
Point 3° of paragraph I of Article L. 442-1 penalises imposing logistics penalties that do not comply with Article L. 441-17. The latter, in the version resulting from Law No. 2023-221 of 30 March 2023, imposes precise constraints. Penalties must be proportionate to the harm suffered in view of the non-performance, within the limit of a ceiling equivalent to 2% of the value of the products ordered falling within the product category in which the non-performance of contractual commitments was found. No penalty may be imposed for non-performance that occurred more than one year earlier. The distributor must, together with the penalty notice, provide by any means proof of the breach found and of the harm suffered. Automatic deduction of the amount from the invoice is prohibited. Only situations that have led to stock shortages in principle justify the application of penalties, the distributor being able to depart from this if it demonstrates and documents in writing the existence of harm. In the event of force majeure, no penalty may be imposed. The text does not apply to relations with wholesalers within the meaning of paragraph II of Article L. 441-4.
For a supplier's chief financial officer, the exposure can be quantified: go back over the penalty notices of recent financial years, set aside those concerning breaches more than a year old, recalculate the 2% ceiling by product category, isolate the automatic deductions. The amount thus reconstructed constitutes both a potential claim for repayment and a negotiating argument.
Price, unilateral revision and indexation
Article 1164 of the Civil Code authorises, in framework agreements, unilateral fixing of the price by one of the parties, on condition that it gives reasons for the amount in the event of a challenge. In the event of abuse, the judge may be asked to award damages and, where applicable, to terminate the contract. A unilateral price clause is therefore not unlawful in itself, and abuse does not entail its nullity. This point is regularly misunderstood: the sanction is compensatory, and possibly termination.
Whether review under L. 442-1, I, 2° may extend to the price itself is a matter for case law, in particular the litigation between the Minister for the Economy and retail purchasing groups. The exclusion of the main subject matter of the contract and of the adequacy of the price to the performance appears in Article 1171 of the Civil Code, not in Article L. 442-1. The absence of that limitation in the commercial text is one of the reasons why claimants favour this basis.
Volumes, exit and competitive tendering
The new paragraph of II requires clauses on volumes to be reread. A stipulation allowing the buyer to reduce the quantities ordered at its discretion, with neither a floor nor notice, is now exposed on two fronts: significant imbalance under 2° and substantial reduction of volumes under II. Likewise, clauses organising periodic re-tendering of the incumbent supplier must be tested against the new 6°, in view of their frequency and their arrangements.
The mirror method
Beyond the clauses named by the Code, the audit proceeds by symmetry. Each stipulation is read with the parties reversed: is the right to terminate open to both? Are notice periods identical? Do liability caps operate in both directions? Are payment periods and settlement conditions consistent with the supplier's CGV? Does the exclusivity granted have a quantifiable counterpart? An asymmetry is not wrongful in itself; it calls for a counterpart to be identified. Where no counterpart is identifiable and the clause was not discussed, the risk materialises. Article 1190 of the Civil Code adds support for the party on the receiving end: in case of doubt, a standard-form contract (contrat d'adhésion) is interpreted against the party that proposed it.
Two competing bases: the Commercial Code and the Civil Code
The manager must choose the ground. The regime on unfair clauses between businesses is not unique.
Article L. 442-1, I, 2° of the Commercial Code is a liability provision. It targets the author of the practice, requires submission or an attempt to submit, and contains no exclusion relating to the main subject matter or the price.
Article 1171 of the Civil Code, in the version resulting from Law No. 2018-287 of 20 April 2018 applicable to acts concluded or drawn up from 1 October 2018, provides that in a standard-form contract, any non-negotiable clause, determined in advance by one of the parties, which creates a significant imbalance between the rights and obligations of the parties, is deemed unwritten. The second paragraph specifies that the assessment of significant imbalance concerns neither the main subject matter of the contract nor the adequacy of the price to the performance. Entry into the text requires a standard-form contract, defined by Article 1110 as one which contains a set of non-negotiable clauses, determined in advance by one of the parties. The 2016 wording, which referred to general conditions removed from negotiation, no longer applies.
The differences are operational. Under Article 1171, the clause is deemed unwritten, that is to say erased, without any need to show a relationship of submission; but the price and the main subject matter escape review, and only the non-negotiable clause is caught. Under Article L. 442-1, the sanction is compensation for the harm, nullity requiring a specific claim based on Article L. 442-4. The relationship between these two texts, and with Article L. 212-1 of the French Consumer Code, is settled by none of the applicable texts: it is a question for doctrine and case law, to be investigated case by case before the basis of the summons is fixed.
Measuring the exposure: sanctions, claimants, court
Article L. 442-4 structures the risk and should serve as a grid for provisioning.
The action is brought before the competent civil or commercial court by any person with an interest, by the public prosecutor's office, by the Minister for the Economy or by the president of the Competition Authority where the latter finds such a practice in the course of cases within its jurisdiction. Any person with an interest may seek cessation of the practices and compensation for the harm suffered.
By contrast, only the victim party may have the nullity of unlawful clauses or contracts declared and seek restitution of undue advantages. The Minister for the Economy and the public prosecutor's office have the same power, but provided that the victims of those practices are informed, by any means, of the bringing of that action. A widespread formulation must therefore be set aside: the imbalanced clause is not "deemed unwritten" on the basis of Article L. 442-1. Its erasure requires an admissible claim for nullity under Article L. 442-4.
The civil fine may be sought only by the Minister or the public prosecutor's office. Its amount may not exceed the highest of the following three amounts: five million euros; three times the amount of the advantages unduly received or obtained; 5% of the turnover excluding tax achieved in France by the author of the practices in the last financial year closed since the year preceding that in which the practices were implemented. For a group achieving significant turnover in France, the third ceiling is the only relevant one.
Reputational risk is not incidental. Paragraph II of Article L. 442-4 provides that the court systematically orders publication, dissemination or display of its decision or an extract of it, at the expense of the person ordered to pay, with the option of insertion in the report on the operations of the financial year drawn up by the managers, the board of directors or the management board. The judge may attach a daily penalty (astreinte) to the decision. The judge hearing summary proceedings (juge des référés) may order, if need be subject to a daily penalty, the cessation of the abusive practices or any other interim measure: this is the urgent lever for a supplier faced with an automatic deduction or with pressure on volumes during a campaign.
Jurisdiction is specialised. Since Decree No. 2021-211 of 24 February 2021, Article D. 442-3 fixes the seat and territorial jurisdiction of the competent tribunaux judiciaires in metropolitan France and overseas in accordance with the table in Annex 4-2-2, appeals lying exclusively to the Paris Court of Appeal. Bringing the matter before a court that has not been designated exposes the claimant to a loss of time that the commercial timetable rarely tolerates.
For international groups, Article L. 444-1 A, resulting from Law No. 2023-221 of 30 March 2023, makes Chapters I, II and III of Title IV applicable to any agreement between a supplier and a buyer concerning products or services marketed in French territory, declares those provisions to be matters of public policy and confers exclusive jurisdiction on the French courts, subject to compliance with European Union law and with international treaties ratified or approved by France and without prejudice to recourse to arbitration. The reservation concerning arbitration is decisive: an arbitration clause (clause compromissoire) is not neutralised by this text. The concrete relationship with intra-European jurisdiction clauses is a matter for case law. The key terms of such a stipulation and the choice between arbitration and the State courts are dealt with separately in our article on the arbitration clause in B2B contracts.
Finally, the time frame. Article L. 110-4, I of the Commercial Code subjects to a five-year limitation period obligations arising in the course of their trade between traders or between traders and non-traders, if they are not subject to shorter special limitation periods. The text does not fix a starting point, and does not settle the treatment of continuing practices. Any strategy for reconstructing the harm over several financial years requires a specific analysis of this point.
Choosing between renegotiation and litigation
The choice is not made on the legal merit of the clause alone. Four parameters govern it.
The first is residual economic dependence. Suing a buyer that represents a decisive share of turnover exposes the supplier to a reduction in volumes, which is itself now caught by paragraph II of Article L. 442-1. This new paragraph changes the balance of power: retaliation through volumes is no longer neutral ground for the buyer.
The second is the timetable. The 1 March deadline, the term of one, two or three years and the requirement of a written record stating the new element justifying any amendment create identifiable negotiation windows. A challenge formalised before conclusion, by a detailed letter, builds the evidence of the absence of effective negotiation in case litigation becomes unavoidable. Signing without reservation does not prevent action, since the text also covers performance, but it weakens the showing of submission.
The third is the choice of claimant. A business may bring the matter before the specialised court, but it may also document the practice with the administration. An action by the Minister for the Economy opens the way to the civil fine and to systematic publication, sanctions that a private action does not carry. It does, however, involve a loss of control over the timetable and over any settlement outcome.
The fourth is the existence of an alternative lever. Article 1195 of the Civil Code allows, in the event of an unforeseeable change of circumstances making performance excessively onerous for a party that had not agreed to bear the risk, a request for renegotiation, the requesting party continuing to perform its obligations during it. In the event of refusal or failure, the parties may agree to terminate or may jointly ask the judge to adapt the contract; failing agreement within a reasonable time, the judge may, at the request of a party, revise the contract or put an end to it. Hence a systematic audit point: the risk-acceptance clause, very frequent in industrial framework agreements, neutralises this lever. Its removal is often more achievable in negotiation than that of a penalty clause. On the conditions of unforeseeability (imprévision) and the drafting of a hardship clause, see our analysis of unforeseeability in B2B contracts.
The obligation to negotiate, form and perform in good faith, laid down by Article 1104 of the Civil Code and a matter of public policy, frames the whole sequence and is echoed by 5° of paragraph I of Article L. 442-1 for negotiations subject to the statutory timetable.
Conclusion
Significant imbalance is not an argument of principle to be brandished at the end of a negotiation: it is a liability regime, accompanied by a nullity reserved to the victim, a civil fine that can reach 5% of the turnover excluding tax achieved in France and systematic publication of the decision. On the buyer's side, the only robust protection is proof of effective negotiation, clause by clause, kept and dated. On the supplier's side, the value of the case is built before the dispute, through the documentary comparison between the CGV, the sole basis of the negotiation, and the framework agreement actually imposed.
Before the next 1 March deadline, have your framework agreements reviewed on an adversarial basis by an adviser external to the purchasing or sales department: first isolate the clauses that are void by operation of law under Article L. 442-3, recalculate the exposure to logistics penalties against the 2% ceiling and the one-year period, then decide clause by clause between a reasoned amendment and bringing the matter before the specialised court. This review costs only a fraction of the exposure it reveals.
Frequently asked questions
Is Article L. 442-6, I, 2° of the Commercial Code still in force? No, not under that numbering. The practice of submitting a party to obligations creating a significant imbalance is now found in Article L. 442-1, I, 2° of the Commercial Code, in the version resulting from Law No. 2026-796 of 18 August 2026, in force since 20 August 2026. The current Article L. 442-6 penalises a distinct practice, the imposition of a minimum resale price, punishable by a fine of €15,000. Submissions that still cite the old numbering as the text in force need to be redone.
Is an imbalanced clause in a framework agreement automatically void? No. Article L. 442-1 establishes civil liability: it requires the author of the practice to compensate the harm caused. Nullity of unlawful clauses or contracts and restitution of undue advantages fall under Article L. 442-4, I, which reserves that claim to the victim party, and to the Minister for the Economy and the public prosecutor's office provided that the victims are informed, by any means, of the bringing of the action. Only Article 1171 of the Civil Code provides, within its own scope, that the clause is deemed unwritten.
Which court should be seised for an action based on significant imbalance? Disputes relating to the application of Articles L. 442-1 et seq. are assigned to courts whose seat and territorial jurisdiction are fixed by decree. Since Decree No. 2021-211 of 24 February 2021, Article D. 442-3 of the Commercial Code refers to the competent tribunaux judiciaires listed in Annex 4-2-2. Appeals lie exclusively to the Paris Court of Appeal. The judge hearing summary proceedings may, if need be subject to a daily penalty, order the cessation of the abusive practices or any other interim measure.
What is the maximum amount of the civil fine? The Minister for the Economy and the public prosecutor's office may seek a civil fine whose amount may not exceed the highest of the following three amounts: five million euros, three times the amount of the advantages unduly received or obtained, or 5% of the turnover excluding tax achieved in France by the author of the practices in the last financial year closed since the year preceding that in which the practices were implemented. To this is added publication, dissemination or display of the decision, which the court systematically orders at the expense of the person ordered to pay.
Is a clause prohibiting the supplier from assigning its receivables valid? No. Article L. 442-3, c) of the Commercial Code, in the version resulting from Law No. 2020-1508 of 3 December 2020, renders void clauses or contracts allowing the counterparty to be prohibited from assigning to third parties the claims it holds. This nullity is incurred independently of any showing of submission. The point must be checked in any framework agreement secured on trade receivables financing.
Can logistics penalties be deducted directly from invoices? No. Article L. 441-17 prohibits the automatic deduction from the amount of the invoice issued by the supplier of penalties or discounts corresponding to non-compliance with a contractual commitment. The distributor must, together with the penalty notice, provide by any means proof of the breach found and of the harm suffered, the supplier having a reasonable period to check and challenge. Failure to comply with Article L. 441-17 is penalised by 3° of paragraph I of Article L. 442-1.
Does a foreign-law or foreign-jurisdiction clause make it possible to avoid this regime? Article L. 444-1 A of the Commercial Code, resulting from Law No. 2023-221 of 30 March 2023, applies Chapters I, II and III of Title IV to any agreement between a supplier and a buyer concerning products or services marketed in French territory, declares those provisions to be matters of public policy and confers exclusive jurisdiction on the French courts. That jurisdiction applies subject to compliance with European Union law and with international treaties ratified or approved by France, and without prejudice to recourse to arbitration. An arbitration clause therefore retains its effect, which makes it a point to be decided as early as the drafting of the framework agreement.
The simulator below estimates the notice period expected and the compensation corresponding to the missing notice.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationA dispute between shareholders that is dragging on?
A contested decision, information withheld, a director who overrides the others: the time to react is counted in months, sometimes in weeks.