A general contractor wins a heavy renovation contract, subcontracts the technical package, collects the interim payment applications, then stops paying its subcontractor. Three months later, the project owner (maître d'ouvrage) receives a formal notice from the unpaid subcontractor, while the court-appointed insolvency practitioner (mandataire judiciaire) of the main contractor claims the balance of the contract and the bank that is assignee of a Dailly receivable (cession Dailly) gives notice of its assignment. Everyone demands to be paid out of the same pot. The question is no longer whether to pay, but to whom, within what limit, and how to avoid paying twice for the same work. This analysis compares the three mechanisms that organise this triangle in French law, payment delegation (délégation de paiement) under Articles 1336 et seq. of the French Civil Code, direct action (action directe) under the Law of 31 December 1975 and direct payment in public contracts, in order to identify precisely the extent of the commitment entered into by the project owner under each of them.
Payment delegation within the meaning of Article 1336 of the Civil Code: a commitment, not an instruction
Order No. 2016-131 of 10 February 2016 codified delegation in Articles 1336 to 1340 of the Civil Code, in force since 1 October 2016. Former Articles 1275 and 1276 no longer exist in this wording, which makes deed templates and cross-reference clauses predating that date obsolete, although they are still widely circulated in private contract practice.
"Delegation is an operation by which a person, the delegator, obtains from another, the delegated debtor, that the latter bind itself towards a third person, the beneficiary, who accepts it as debtor." (Article 1336, first paragraph, of the Civil Code)
Transposed to a building site, the structure is as follows: the main contractor is the delegator, the project owner the delegated debtor, the subcontractor the beneficiary. Two conditions emerge from the text and determine the characterisation: the project owner must bind itself, that is, enter into a commitment towards the subcontractor, and the subcontractor must accept it as debtor. A letter in which the main contractor asks the project owner to pay its subcontractor directly meets neither of these two conditions.
Article 1340 says so unambiguously: "The mere indication by the debtor of a person designated to pay in its place entails neither novation nor delegation. The same applies to the mere indication, by the creditor, of a person designated to receive payment on its behalf." The distinction is operative. A mere payment instruction leaves the project owner debtor of the main contractor alone; it pays on the latter's behalf, and the subcontractor has no right of its own against it. A delegation, by contrast, creates a new obligation of the project owner towards the subcontractor, with its own regime.
The second paragraph of Article 1336 lays down the rule that is both the interest and the danger of the mechanism: "The delegated debtor may not, unless otherwise stipulated, raise against the beneficiary any defence arising from its relations with the delegator or from the relations between the latter and the beneficiary." In other words, as a principle, the delegated project owner cannot raise against the subcontractor either the defects attributable to the main contractor, or late-delivery penalties, or termination of the main contract, or a dispute between the main contractor and its subcontractor. Two words govern the whole drafting of the deed: unless otherwise stipulated. The unenforceability of defences is not a matter of public policy; it is a default rule. A project owner that does not expressly derogate from it therefore commits itself on the most rigorous terms.
Imperfect or perfect delegation: what the subcontractor gains, what the main contractor does not lose
The distinction between perfect and imperfect delegation governs the whole operation, and Article 1337 sets the criterion:
"Where the delegator is a debtor of the beneficiary and the beneficiary's intention to discharge the delegator results expressly from the deed, the delegation operates novation."
Discharge is therefore never presumed. It must result expressly from the deed. The same article reserves two cases in which the delegator remains liable despite the novation: if it has expressly undertaken to guarantee the future solvency of the delegated debtor, or if the latter is subject to a debt-clearance procedure at the time of the delegation.
Failing express discharge, it is Article 1338 that applies: "Where the delegator is a debtor of the beneficiary but the latter has not discharged it from its debt, the delegation gives the beneficiary a second debtor. Payment made by one of the two debtors releases the other, to the extent of that payment." This is imperfect delegation. The subcontractor keeps its contractual debtor, the main contractor, and acquires a second debtor, the project owner. There is no substitution but addition. Extinction occurs to the extent of the payments made, which rules out any double recovery by the subcontractor but requires rigorous allocation accounting.
For the project owner, this characterisation is not neutral. In an imperfect delegation, it does not absorb the main contractor's debt: it adds its own commitment to that of the original debtor. The subcontractor keeps all of its remedies against the main contractor, including for the portion that the project owner does not cover.
Why the 1975 Law requires imperfect delegation: Article 14 and the surety on pain of nullity
In private contracts, payment delegation is not a mere contractual convenience negotiated between professionals. It is the statutory alternative to a guarantee whose absence is sanctioned by nullity of the subcontract. Article 14 of Law No. 75-1334 of 31 December 1975 on subcontracting provides that "on pain of nullity of the subcontract, payment of all sums owed by the contractor to the subcontractor under that subcontract is guaranteed by a personal and joint and several surety obtained by the contractor from a qualified institution, approved under conditions set by decree".
The same article immediately opens the safety valve:
"However, the surety need not be provided if the contractor delegates the project owner to the subcontractor on the terms of Article 1338 of the Civil Code, up to the amount of the services performed by the subcontractor."
This cross-reference deserves attention. The Order of 10 February 2016 amended Article 14 by its Article 6: the earlier version referred to Article 1275 of the Civil Code, the version in force refers to Article 1338. The text therefore expressly requires an imperfect delegation. A novating delegation, by which the subcontractor would expressly discharge the main contractor, does not meet the statutory condition for dispensing with the surety. A badly drafted deed can thus miss its primary function, leave the surety requirement in place and expose the subcontract to nullity.
Article 14 also sets the reference perimeter of the exemption: "up to the amount of the services performed by the subcontractor". The delegation in Article 14 is therefore not conceived as a general guarantee of the subcontract, but as cover indexed to actual performance. The other clauses to be secured in the subcontract are listed in our legal guide to the construction subcontract.
Article 14-1 completes the scheme with policing obligations on the project owner in building and public works contracts. If it is aware of the presence on the site of a subcontractor that has not been the subject of the obligations defined in Article 3 or Article 6, as well as those defined in Article 5, it must serve formal notice on the main contractor or the subcontractor to comply, these provisions applying to public and private contracts alike. Above all, "if the accepted subcontractor, whose payment terms have been approved by the project owner under the conditions defined by decree of the Conseil d'Etat, does not benefit from payment delegation, the project owner must require the main contractor to prove that it has provided the surety". Delegation is therefore not only an instrument for securing the subcontractor: its absence triggers a duty of verification on the project owner. These obligations do not apply to a natural person building a home to occupy it personally or to have it occupied by their spouse, ascendants, descendants or those of their spouse.
For subcontracting chains, Article 6 of the 1975 Law adds that a subcontractor who entrusts to another subcontractor the performance of part of the contract for which it is responsible must provide it with a surety or a payment delegation under the conditions defined in Article 14.
Delegation and direct action: two bases, two ceilings
This is where the project owner's choice is made. Direct action and delegation produce a similar economic result, payment of the subcontractor by the project owner, but their perimeters follow opposite logics.
Direct action is capped by law
Article 12 of the 1975 Law gives the subcontractor a direct action against the project owner "if the main contractor does not pay, one month after being served formal notice, the sums due under the subcontract; a copy of this formal notice is sent to the project owner". The text adds that "any waiver of direct action is deemed unwritten" and that the action survives even if the main contractor is subject to collective insolvency proceedings, the wording still referring to liquidation of assets, judicial settlement and provisional suspension of proceedings. Article 12, fourth paragraph, also makes applicable to a subcontractor meeting these conditions the second paragraph of Article 1799-1 of the Civil Code, on the allocation of the specific loan taken out by the project owner.
The ceiling is in Article 13:
"Direct action may relate only to payment corresponding to the services provided for in the subcontract and from which the project owner actually benefits. The project owner's obligations are limited to what it still owes the main contractor on the date of receipt of the copy of the formal notice provided for in the preceding article."
Two cumulative limits, then, and strictly statutory. First a substantive criterion, the services under the subcontract from which the project owner actually benefits. Second an accounting criterion crystallised at a precise date, that of receipt of the copy of the formal notice. A project owner that has already paid the main contractor in full at that date owes nothing to the subcontractor under direct action. This is the statutory protection against double payment. The triggering event of this remedy and the project owner's decision timetable are detailed in our article on the subcontractor's direct action.
Delegation is capped by the deed, not by law
Nothing of the kind exists in Articles 1336 et seq. of the Civil Code. The extent of the delegated debtor's commitment results from the terms of the deed of delegation. The limit in Article 13, specific to direct action, is not transposed automatically to delegation. A project owner that signs a deed of delegation drafted with no ceiling, no indexation to progress and no reservation of defences therefore potentially commits itself beyond what it would owe under direct action, and beyond what it still owes the main contractor.
The difference can be measured on four parameters:
- the base: limited by law to the services from which the project owner actually benefits in direct action, set by the deed in delegation;
- the ceiling: what the project owner still owes the main contractor on the date of receipt of the copy of the formal notice in direct action, the amount stipulated in delegation;
- the means of defence: the unenforceability of defences under Article 1336 operates in principle against the delegated debtor, unless otherwise stipulated, whereas direct action remains tied to the claim under the main contract;
- the trigger: direct action requires a formal notice that has remained unsuccessful for one month and receipt of its copy, whereas delegation takes effect as soon as the subcontractor accepts the project owner as its debtor.
The question whether the subcontractor beneficiary of a delegation keeps, and to what extent, the exercise of the direct action in Article 12 is not settled by the texts. Article 12 deems any waiver of direct action unwritten, which calls for caution in drafting: a clause in the deed of delegation presented as excluding direct action exposes the project owner to a challenge. The combination of the two routes must therefore be handled by an allocation mechanism, not by an exclusion clause.
Direct payment in public contracts is a separate regime
Confusion between delegation, direct action and direct payment remains frequent in mixed structures, where the same operator acts as private project owner on one asset and as holder of a public contract on another.
Direct payment falls under the French Public Procurement Code. Article L. 2193-11 provides that "the direct subcontractor of the contract holder that has been accepted and whose payment terms have been approved by the purchaser is paid directly by the latter for the part of the contract it performs. Any waiver of direct payment is deemed unwritten." Article L. 2193-12 adds that direct payment is mandatory even if the contract holder is in judicial liquidation, judicial reorganisation or safeguard proceedings.
The interaction with the 1975 Law is dealt with by Article L. 2193-10: the accepted and approved subcontractor is paid under the conditions of the Public Procurement Code where the amount of the subcontract is equal to or greater than a threshold set by regulation, and under the conditions of Title III of the 1975 Law, that is, by direct action, where that amount is below the threshold. Article 6 of the 1975 Law, for its part, uses a threshold of €600, below which the provisions of Title III apply.
The practical consequence is clear. In a public contract, the purchaser does not have to negotiate a delegation: direct payment is imposed on it by operation of law, for the benefit of the accepted and approved subcontractor. In a private contract, no equivalent mechanism exists. Delegation is the contractual tool that comes closest, but it has neither its automatic nature nor its limits.
Article 1339, the lock against double payment
Article 1339 of the Civil Code is the decisive text for the delegated project owner, because it governs the fate of the claim the main contractor holds against it.
"Where the delegator is a creditor of the delegated debtor, its claim is extinguished only by performance of the delegated debtor's obligation towards the beneficiary and to the extent of that performance. Until then, the delegator may demand or receive payment of it only for the portion exceeding the delegated debtor's commitment. It recovers its rights only by performing its own obligation towards the beneficiary. Assignment or seizure of the delegator's claim takes effect only subject to the same limitations."
Three lessons for the project owner's finance department.
First, as long as the project owner has not performed its commitment towards the subcontractor, the main contractor's claim against it subsists, but it is unavailable up to the amount of the delegated commitment. The main contractor may demand or receive payment of it only for the portion exceeding that commitment. A project owner that nonetheless paid the main contractor the whole of the interim payment application would risk having to pay the subcontractor beneficiary a second time.
Second, and this is the decisive contribution on site refinancing, assignment or seizure of the delegator's claim takes effect only subject to the same limitations. The bank that is assignee of a Dailly receivable, like the seizing creditor, takes the claim only reduced by the delegated commitment. This rule combines with Article 13-1 of the 1975 Law, under which the main contractor may assign or pledge the receivables arising from the contract only up to the sums owed to it for the works it carries out personally, unless it has first obtained in writing the personal and joint and several surety of Article 14 for the benefit of the subcontractors. The formalities of the assignment schedule (bordereau) and the assignee's ranking are dealt with separately in our article on the Dailly assignment and the mobilisation of business receivables.
Third, Article 1339 closes the loop in the opposite direction: "However, if the beneficiary has released the delegator, the delegated debtor is itself released towards the delegator, up to the amount of its commitment towards the beneficiary." A settlement between the subcontractor and the main contractor is therefore not a matter of indifference to the project owner, which must be informed of it by contract.
Drafting choices on the project owner's side
Delegation is a three-party act. The project owner that accepts it must deal with the following points in the deed itself.
First, characterisation. The deed must expressly refer to Article 1338 of the Civil Code and Article 14 of the 1975 Law, and exclude any discharge of the main contractor, failing which the exemption from the surety is not secured and the project owner finds itself sole debtor. The wording must be positive: the subcontractor accepts the project owner as second debtor without discharging the main contractor.
Second, perimeter. The ceiling of the commitment, the rhythm at which it falls due and its base must be stipulated. Article 14 provides a useful benchmark by referring to the amount of the services performed by the subcontractor. A delegation tied to the works payment applications validated by the project management team (maîtrise d'œuvre), and capped in amount, stays within the logic of the law; a lump-sum delegation disconnected from progress turns the project owner into an independent guarantor.
Third, defences. As Article 1336 is a default rule, it is for the project owner to reserve, by express clause, the defences it intends to keep. Failing that, it will be able to raise against the subcontractor neither disputes arising from the main contract, nor those arising from the subcontract. The practical scope of this unenforceability in subcontracting calls for case-by-case analysis and a check of case law at the date of negotiation.
A payment discipline is added to this. The allocation must be kept in a single account, application by application, to trace what has been paid under the delegation, what remains due to the main contractor and what exceeds the delegated commitment. It is this traceability, more than the clause, that makes it possible to resist a competing claim from the insolvency practitioner, the Dailly assignee or the subcontractor exercising direct action.
Conclusion
The well-advised project owner reasons not in terms of goodwill but of exposure. Direct action under Articles 12 and 13 of the 1975 Law is suffered, but it is bounded by law: never more than what remains due to the main contractor on the day the copy of the formal notice is received. The imperfect delegation of Article 1338 is chosen, but it is bounded only by the deed, and the unenforceability of defences in Article 1336 operates by default against the delegated debtor. Direct payment under the Public Procurement Code concerns public contracts only and does not carry over.
Accepting a delegation often remains the right choice: it exempts the main contractor from the surety in Article 14, it neutralises, by the effect of Article 1339, the Dailly assignment and seizure over the delegated portion, and it avoids direct action litigation during the works. But it protects against double payment only if it is drafted to do so. Before signing any deed of delegation, have three points checked by an adviser: that the deed refers to Article 1338 without discharging the main contractor, that it caps the commitment and indexes it to the services actually performed, and that it expressly reserves the defences arising from the main contract. A deed signed on the basis of a template predating 1 October 2016, still referring to Article 1275 of the Civil Code, must be redrafted in full.
Frequently asked questions
Does a payment delegation exempt the main contractor from providing the surety in Article 14?
Yes, but on strict conditions. Article 14 of the Law of 31 December 1975 provides that the surety need not be provided if the contractor delegates the project owner to the subcontractor "on the terms of Article 1338 of the Civil Code, up to the amount of the services performed by the subcontractor". The delegation must therefore be imperfect, that is, it must not discharge the main contractor from its debt. A novating delegation within the meaning of Article 1337 does not meet this condition. It should be recalled that the surety requirement is sanctioned by nullity of the subcontract.
Can a subcontractor benefiting from a delegation still exercise direct action?
Article 12 of the 1975 Law deems any waiver of direct action unwritten, which makes any clause in the deed of delegation that purports to exclude it hazardous. The texts do not expressly settle how the two routes interact, and the question calls for an up-to-date check of case law before any negotiation. In practice, the project owner protects itself less by an exclusion clause than by an allocation mechanism: Article 1338 provides that payment made by one of the debtors releases the other to the extent of that payment, which rules out any double payment to the subcontractor.
Up to what amount is the project owner liable under direct action?
Article 13 of the 1975 Law lays down two cumulative limits. Direct action may relate only to payment corresponding to the services provided for in the subcontract and from which the project owner actually benefits. And the project owner's obligations are limited to what it still owes the main contractor on the date of receipt of the copy of the formal notice provided for in Article 12. The date of receipt of that copy therefore crystallises the base, which makes time-stamping and retention of the letter received essential.
Does a Dailly assignment granted by the main contractor take priority over the payment delegation?
No, for the delegated portion. Article 1339 of the Civil Code states that the delegator's claim against the delegated debtor is extinguished only by performance of the delegated debtor's obligation towards the beneficiary and to the extent of that performance, and that "assignment or seizure of the delegator's claim takes effect only subject to the same limitations". The assignee and the seizing creditor therefore take the claim only reduced by the delegated commitment. Article 13-1 of the 1975 Law also limits assignment or pledge to the sums owed to the main contractor for the works it carries out personally, unless a prior written surety has been provided for the benefit of the subcontractors.
What is the difference between direct payment and direct action?
Direct payment is the regime for public contracts. Article L. 2193-11 of the Public Procurement Code provides that the accepted direct subcontractor whose payment terms have been approved by the purchaser is paid directly by it for the part of the contract it performs, any waiver being deemed unwritten, and Article L. 2193-12 makes it mandatory even in judicial liquidation, judicial reorganisation or safeguard proceedings of the contract holder. Direct action under Article 12 of the 1975 Law is the regime for private contracts and requires a formal notice that has remained unsuccessful for one month. Article L. 2193-10 of the Public Procurement Code moreover refers to Title III of the 1975 Law where the amount of the subcontract is below the threshold set by regulation.
Does a transfer order sent by the main contractor amount to a delegation?
No. Article 1340 of the Civil Code expressly rules out this characterisation: "The mere indication by the debtor of a person designated to pay in its place entails neither novation nor delegation." Delegation requires, under Article 1336, that the project owner bind itself towards the subcontractor and that the latter accept it as debtor. A tripartite deed signed by all three parties is therefore necessary; a bilateral instruction between the main contractor and the project owner creates no right of its own for the subcontractor and does not dispense with the surety in Article 14.
Must the project owner check that a guarantee exists for the subcontractors?
Yes, in building and public works contracts. Article 14-1 of the 1975 Law requires the project owner, if it is aware of the presence on the site of a subcontractor that has not been the subject of the obligations in Articles 3, 5 or 6, to serve formal notice on the main contractor or the subcontractor to comply, in public and private contracts alike. The same article adds that if the accepted and approved subcontractor does not benefit from payment delegation, the project owner must require the main contractor to prove that it has provided the surety. These obligations do not apply to a natural person building a home to occupy it personally or to have it occupied by their spouse, ascendants, descendants or those of their spouse.
The simulator below tells you, from the date of acceptance of the works, which guarantee covers your defect and until when you can act.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationDefects that appeared after handover?
One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.