A French supplier delivers goods to a customer established in Poland, Spain or the Netherlands, the invoice remains unpaid, and the question facing the finance department is no longer whether the debt is well founded but which procedural vehicle to use: a French enforceable title, a European order for payment (injonction de payer européenne), or a protective measure before any debate on the merits? The three European instruments for cross-border recovery do not address the same situation, do not withstand the same degree of challenge and do not trigger the same time limits. The wrong choice is not paid for in procedural costs but in months lost while the debtor's assets move. This guide sets out the choice between the European order for payment, the European Enforcement Order (titre exécutoire européen) and the European Account Preservation Order (saisie conservatoire européenne des comptes bancaires), then presents the procedural chronology as a decision calendar: which step starts which time limit, and from what point the debt becomes difficult to enforce.
Three regulations, three distinct logics
The most frequent confusion consists in treating these instruments as variants of a single procedure. They operate at different stages of the life of a debt.
Regulation (EC) No 1896/2006 of 12 December 2006 establishes a European order for payment procedure. It creates an enforceable title where none exists, through a non-adversarial procedure based on standard forms, applicable since 12 December 2008.
Regulation (EC) No 805/2004 of 21 April 2004 creating a European Enforcement Order for uncontested claims does not create any title. It certifies a title already obtained (judgment, court settlement, authentic instrument) so that it circulates without exequatur (a declaration of enforceability) in the other Member States. It has been applicable since 21 October 2005.
Regulation (EU) No 655/2014 of 15 May 2014 establishes the European Account Preservation Order, applicable since 18 January 2017. It decides nothing on the merits: it freezes assets, where appropriate even before any decision has been made.
Two further reference texts must be added, which no serious analysis can ignore: Regulation (EU) No 1215/2012, known as Brussels I bis, which determines jurisdiction and abolished exequatur for judgments given in proceedings instituted on or after 10 January 2015, and Regulation (EU) 2020/1784 on the cross-border service of documents, applicable since 1 July 2022.
Territorial scope is a first-stage sorting criterion. Denmark is excluded from the three specific regulations. Ireland takes part in the European order for payment, the European Enforcement Order and the European Account Preservation Order. The United Kingdom has been outside the system since 1 January 2021. Switzerland, Norway and Iceland have only ever been covered by the Lugano Convention of 30 October 2007.
The European order for payment: speed against fragility
Conditions of access and exclusions
The European order for payment covers pecuniary claims that are liquidated and due in civil and commercial matters, in a cross-border dispute within the meaning of Article 3 of Regulation 1896/2006, that is, where at least one of the parties is domiciled or habitually resident in a Member State other than that of the court seised. Article 2 excludes in particular matrimonial property regimes, bankruptcies and similar proceedings, social security, and claims arising from non-contractual obligations save for limited exceptions.
Jurisdiction is determined by reference to the Brussels I bis Regulation (Article 6 of Regulation 1896/2006). This cross-reference is the most underused lever among French creditors. A jurisdiction clause validly agreed within the meaning of Article 25 of Brussels I bis, or failing that the head of jurisdiction based on the place of performance of the obligation provided for in Article 7(1)(b) (place of delivery of the goods, place of provision of the services), frequently makes it possible to bring the matter before a French court. The procedure then takes place in France, in French, and the title is subsequently enforced directly in Spain or Romania. Where the defendant is a consumer, Article 6(2) conversely requires jurisdiction to lie with the courts of the Member State of the consumer's domicile.
The application: what is at stake in completing Form A
The application is made using Form A annexed to the Regulation. Its content, set out in Article 7, is more demanding than it appears: identification of the parties, principal amount, interest and its starting point, the cause of action, a description of the evidence, and justification of the cross-border nature of the case. The court does not require the documents to be produced; it examines the apparent coherence of the application. A poorly completed form triggers a request to complete (Form B) or a proposal to modify (Form C), each of which consumes time.
The interest item deserves particular attention. The Court of Justice of the European Union accepts that the applicant may claim interest up to the date of actual payment, including where the national law of the court seised organises its calculation differently. For an institutional creditor facing delays of several quarters, the cumulative gain is not marginal, provided the application was correctly worded from the outset.
The thirty-day period: the pivot of the whole strategy
The court rules in principle within thirty days of the lodging of the application, not counting time for completion or modification (Article 12). The order is issued using Form E, then served on the defendant in accordance with Articles 13 to 15.
This service stage is the real breaking point. The permitted methods of service require either an acknowledgment of receipt by the defendant (Article 13) or, failing that, methods offering a high degree of certainty as to receipt (Article 14). Fictitious service is excluded: where the debtor's address is not known with certainty, the European order for payment is not available, the Court of Justice having ruled out service by publication in this context. A debtor whose declared registered office no longer corresponds to a real establishment therefore neutralises the instrument.
From service, the defendant has thirty days to lodge a statement of opposition using Form F (Article 16). The opposition need not be reasoned. It is enough to send the dispute into ordinary civil proceedings before the courts of the Member State of origin, unless the applicant has expressly requested, in Appendix 2 to Form A, that the proceedings be terminated in the event of opposition.
Where there is no opposition within the time limit, the court of origin declares the order enforceable without delay (Form G, Article 18). Article 19 abolishes any exequatur procedure: the title is recognised and enforced in the other Member States without any intermediate declaration. The only grounds for refusal of enforcement open to the debtor are irreconcilability with an earlier decision and payment (Article 22), in addition to review in the exceptional cases of Article 20, which is interpreted restrictively.
When to give up on the European order for payment
The instrument is designed for claims that the debtor will not contest. Faced with a debtor who has already written to challenge the conformity of a delivery, to plead set-off or to dispute a calculation of interest, the European order for payment merely adds a detour: a formal opposition within thirty days, then a resumption on the merits, with a net loss of several months. The rule for choosing is simple: the higher the likelihood of challenge, the more the creditor should go directly to the court on the merits and secure the assets in parallel. Where the French court has jurisdiction, the routes open before it are presented in our article on bringing an unpaid invoice before the commercial court.
The European Enforcement Order: certifying a title already obtained
The notion of uncontested claim
Regulation 805/2004 applies only to uncontested claims within the meaning of its Article 3. Four situations are covered: express acknowledgement by the debtor in the course of the proceedings; a settlement approved by or concluded before a court; the debtor's failure to object in accordance with the law of the State of origin, which covers default judgments; and failure to appear at a hearing after an initial challenge.
A French judgment given by default against a German company, a national order for payment (ordonnance d'injonction de payer) that has become enforceable for lack of opposition, a notarial deed containing an acknowledgement of debt: all potentially qualify for certification. The certificate is issued using the form set out in Annex I. Under domestic law, the application for certification is made, depending on the nature of the title, to the head of the registry services (directeur des services de greffe) of the court that ruled or to the notary holding the deed, in accordance with Articles 509-1 et seq. of the French Code of Civil Procedure. The steps of the domestic procedure, from the application to the enforcement formula, are detailed in our article on the order for payment procedure to recover a B2B invoice.
The minimum standards for service: the weak point
The counterpart of the abolition of exequatur is found in Articles 12 to 19 of Regulation 805/2004. Certification is possible only if the original proceedings complied with minimum standards concerning service of the document instituting proceedings and information given to the debtor about the claim and about the steps required to contest it. A summons served on a foreign registered office without compliance with the service regulation, or a decision that does not mention the available remedies, closes the route to certification.
This is an operational consequence that is rarely anticipated: the certifiability of a judgment is prepared at the summons stage, not after the judgment is delivered. An institutional creditor bringing an action against an intra-EU debtor should, from the moment the originating document is served, document the methods of service with a view to the future certification.
European Enforcement Order or Brussels I bis: the real choice
Since the Brussels I bis Regulation came into application, any judgment given in a Member State is enforceable in the others without exequatur, on production of the certificate provided for in Article 53. The residual interest of the European Enforcement Order lies in the nature of the review left to the debtor.
Under Brussels I bis, the debtor retains the right to apply to the court of the State of enforcement for refusal of enforcement on the grounds set out in Articles 45 and 46, in particular contravention of public policy and failure to serve the document instituting proceedings in due time and in a regular manner. Under Regulation 805/2004, those grounds disappear: the only possible refusal is irreconcilability with an earlier decision (Article 21), the debtor having only a right of review in the State of origin (Article 19).
The choice can be put as follows: where the debtor has never appeared and resistance to enforcement is likely, certification as a European Enforcement Order closes a route of challenge that Brussels I bis would leave open. Where the debtor has appeared and argued its case, the Article 53 certificate is sufficient.
The European Account Preservation Order: the effect of surprise
Two regimes depending on whether or not the creditor holds a title
Regulation 655/2014 establishes a non-adversarial procedure: the debtor is informed only after the measure has been executed (Article 11). It is the instrument that preserves the basis of recovery where the debtor arranges for the mobility of its cash.
The conditions differ according to the creditor's situation. If the creditor does not yet hold a judgment, a court settlement or an authentic instrument, it must establish cumulatively the apparent merit of its claim and urgency, defined in Article 7 as the real risk that subsequent enforcement of the claim will be impeded or made substantially more difficult. If it already holds such a title, only urgency must be shown. The court may make the measure subject to the provision of security (Article 12), which is in principle required where the creditor does not yet hold a title. By way of comparison, the conditions and time limits of the domestic measure are dealt with separately in our article on protective attachment before judgment.
The time limits imposed on the court are short: Article 18 provides for a decision within ten working days of the lodging or completion of the application where the creditor has no title, and five working days where it holds one. The receiving bank implements the order without delay and sends a declaration concerning the funds attached within three working days (Article 25).
The request for information on bank accounts
Article 14 allows a creditor who does not know its debtor's bank details to ask the court to send a request for information to the competent authority of the Member State of enforcement. This option is broadly available to a creditor holding an enforceable title, and more restricted where the title is not yet enforceable. In France, this information authority role is performed by commissaires de justice (bailiffs), who have access to bank account registers.
For a bank or an institutional lender facing a debtor that has moved its flows to an institution located in another Member State, this mechanism changes the position: it turns a claim that is theoretically enforceable but in practice without any attachable base into an effective measure.
The obligation to bring proceedings on the merits
Article 10 imposes strict procedural discipline. Where the order was obtained before proceedings on the substance were commenced, the creditor must initiate those proceedings and provide proof of this to the court within thirty days of the date of lodging the application for the order, or within fourteen days of the date of issue of the order, whichever is the later. Failing this, the order is revoked or ceases to have effect. The protective attachment is therefore never an end in itself: it is the first act of a sequence whose second act is already dated.
The decision calendar: which step starts which time limit
The value of a cross-border claim decreases over time along a curve that the creditor controls only in part. The tipping points can be identified.
- Limitation: in commercial matters, an action between traders or between traders and non-traders is time-barred after five years (Article L. 110-4 of the French Commercial Code), a claim brought before the courts interrupting the limitation period under the conditions of Article 2241 of the French Civil Code. A formal notice (mise en demeure), by contrast, interrupts nothing.
- Issue of the European order for payment: starting point of the period for service.
- Service of the order: starts the thirty days for opposition under Article 16 of Regulation 1896/2006. It is the most structuring time limit, because its expiry without opposition turns an application on forms into an enforceable title in twenty-six Member States.
- Issue of the preservation order: starts the fourteen days of Article 10 of Regulation 655/2014, combined with the thirty days running from the application.
- The opening of insolvency proceedings in the State of the debtor's centre of main interests, within the meaning of Regulation (EU) 2015/848: the stay of individual actions neutralises enforcement measures and requires a switch to the filing of claims in the foreign proceedings, with their own forfeiture periods.
This last point governs the hierarchy of priorities. Between the moment an intra-EU debtor stops paying and the moment collective proceedings open in its State of establishment, the useful window is counted in weeks. A creditor that spends that time pursuing a European order for payment without a parallel protective measure will obtain a perfectly valid title over a non-existent base.
Choosing according to the debtor's profile
Four configurations are encountered in practice.
A solvent, identified debtor whose challenge is unlikely falls within the European order for payment before the French court having jurisdiction by virtue of a jurisdiction clause or the place of performance. Costs are contained, representation is not compulsory in many cases, and enforcement abroad is direct.
A structurally contentious debtor, who has already voiced complaints about the performance of the contract, justifies a direct summons on the merits. Subsequent certification as a European Enforcement Order will be excluded if the debtor appears, but the Article 53 certificate of Brussels I bis will ensure that the judgment circulates.
A debtor whose signs of deterioration are identifiable (cascading delays, change of bank, disposal of assets, resignation of directors) calls for a European Account Preservation Order as the first step, followed within the Article 10 time limit by an action on the merits.
A debtor established outside the scope of the regulations requires different reasoning. For Switzerland, Norway and Iceland, the 2007 Lugano Convention provides for recognition subject to a declaration of enforceability. For the United Kingdom, relations rest on the Hague Convention of 30 June 2005 on Choice of Court Agreements and, now, on the Hague Convention of 2 July 2019 on the Recognition and Enforcement of Foreign Judgments, which entered into force for the European Union on 1 September 2023 and has since been ratified by the United Kingdom. For Denmark, which is excluded from the three specific regulations, the parallel agreement with the Union on jurisdiction and enforcement applies.
Operational points of vigilance
Contractual drafting upstream weighs more than the choice of instrument downstream. A jurisdiction clause in favour of the Paris commercial court, complying with the formal requirements of Article 25 of Brussels I bis, secures French jurisdiction for the whole system, including the European order for payment.
Documentation of the claim conditions enforcement. Signed delivery notes, order acceptance, confirmation of receipt, agreed account statements: the European order for payment procedure does not require the documents to be produced, but the ordinary proceedings following an opposition will require them, within a tight time limit.
The language question generates costs and delays. The European Enforcement Order certificate must, where appropriate, be translated into the language of the State of enforcement. The European order for payment form must be completed in a language accepted by the court seised.
Finally, a European Small Claims Procedure exists (Regulation (EC) No 861/2007, whose threshold was raised to €5,000 by Regulation (EU) 2015/2421 with effect from 14 July 2017). It remains marginal for an institutional creditor, but can usefully deal with a disputed balance.
Conclusion
The dominant reflex, which consists in opening a European order for payment at the first cross-border default, reverses the order of priorities. A title without an attachable base is worth nothing. The effective sequence, for an institutional creditor exposed to an intra-EU debtor, is first to assess the risk of dissipation of assets and only then to choose the vehicle for creating or circulating the title. The European Account Preservation Order is the most underused instrument of the system although it is the only one that preserves the real value of the claim; the European order for payment remains unbeatable for uncontested claims; the European Enforcement Order retains a specific interest, that of closing the public policy review and the ground of defective service that Brussels I bis leaves open to defaulting debtors.
Before taking any step, have a three-line choice note prepared on each file: the State of establishment of the debtor and that State's participation in the three regulations, the probability of challenge as documented by previous exchanges, and the existence of indications of dissipation justifying a protective measure. These three parameters determine the instrument. And if your framework contracts do not contain a jurisdiction clause complying with Article 25 of Brussels I bis, that revision comes before any cross-border recovery strategy.
Frequently asked questions
What is the difference between a European order for payment and a European Enforcement Order? The European order for payment, governed by Regulation 1896/2006, is a procedure that creates an enforceable title on the basis of a simple application on Form A, without prior adversarial debate. The European Enforcement Order, governed by Regulation 805/2004, creates nothing: it certifies a title already obtained (judgment, court settlement, authentic instrument) relating to an uncontested claim, so that it circulates without exequatur. The first is used when there is no title, the second when there is one.
Can a European order for payment be obtained against a Danish or Irish debtor? Denmark is excluded from Regulation 1896/2006, Regulation 805/2004 and Regulation 655/2014; enforcement there rests on the parallel agreement concluded with the European Union. Ireland, by contrast, takes part in all three regulations, including the European Account Preservation Order (recital 49 of Regulation 655/2014). This territorial filter must be checked before any choice of instrument.
How long does a European order for payment take? Article 12 of Regulation 1896/2006 provides that the court rules in principle within thirty days of the lodging of the application, not counting time for completion or modification. To this must be added the time for service on the defendant, which varies according to the Member State, then the thirty-day opposition period under Article 16. Where there is no opposition, the declaration of enforceability is made without delay using Form G. A realistic timetable is therefore counted in months, not weeks.
What happens if the debtor lodges an opposition? The opposition, lodged within thirty days of service using Form F, need not be reasoned. The procedure then moves to ordinary civil proceedings before the courts of the Member State of origin, unless the applicant has requested in Appendix 2 to Form A that the proceedings be terminated in the event of opposition. Article 25 of the Regulation regulates costs by providing that the cumulative court fees must not exceed those of ordinary civil proceedings without a prior order for payment.
Does the European Account Preservation Order make it possible to locate the debtor's accounts? Yes. Article 14 of Regulation 655/2014 allows the creditor to ask the court to approach the competent authority of the Member State of enforcement to obtain information on the debtor's accounts. This option is broadly available to a creditor holding an enforceable title, and more restricted otherwise. In France, this role is performed by commissaires de justice.
Is the European Enforcement Order still useful since Brussels I bis? Yes, in one specific case. Regulation 1215/2012 abolished exequatur but leaves the debtor free to apply for refusal of enforcement on the basis of Articles 45 and 46, in particular for contravention of public policy or defective service of the document instituting proceedings. Certification under Regulation 805/2004 closes those grounds in the State of enforcement: enforcement can be refused there, at the debtor's request, only where the judgment is irreconcilable with an earlier decision given between the same parties on the same cause of action, where that irreconcilability could not have been raised in the State of origin, and the judgment may under no circumstances be reviewed as to its substance there (Article 21). The debtor has only the review available in the State of origin in the exceptional cases of Article 19. The interest of certification is therefore concentrated on judgments given by default against a debtor likely to resist enforcement.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationAn invoice that remains unpaid?
Depending on whether or not you hold an enforceable title, and on the age of the debt, the quickest route is not the same.